Introduction

Then create an overview of the environmental conditions. What is the terrain like?

  • Total area Building plan
  • Number of floors
  • Outdoor coverage

How is the building fabric?

  • Materials
  • Type of windows e.g. mirrored glass
  • Planned construction measures  

Which disturbing influences are recognizable?

  • Reinforced concrete
  • Lifts
  • Fire doors
  • Supply lines
Example

In the example below the following environmental conditions are important.

  • Between the office and the Production hall, an fireproof concrete wall is placed.
  • The Production has metal walls.
  • In the reception an waterfall is installed.
  • In the middle an Server room with fireproof concrete walls is placed.
  • Phone calls around the building should be possible.